Handling missing data

Data arrives late. A broker file is delayed, an exchange publishes after the cut-off, a smart curve waits for one of its inputs. A scheduled export has to decide what to send when that happens, and the receiving system has to be able to tell. The Export extension gives you three settings for this, on the schedule's Missing data section.


What counts as missing​

ItemMissing when
TimeSeriesNo values from the start to the end of its range. With The export date only, no value on the export date.
Curve, with The curve for the export dateNo curve for the export date
Curve, with The latest curve on or before the export dateNo curve at all on or before the export date
Curve, with Every curve in the timeseries rangeNo curve in the range
Curve, with Tenors setNone of its curves has a contract in the tenors. The report says so, for example No contracts in the tenors Q05.
Event listNo events in the range that meet its conditions, unless No events is normal for this list is ticked in its filter
Curve saved for one ondate, master dataThe item cannot be read
Any itemThe platform returns an error, for example the item was deleted or you have no access to it. The report shows the reason.

Gaps inside a timeseries range are a separate setting: the item has values, but not on every date.


When an item has no data​

ChoiceWhat the export doesStatus in the report
Leave the item outExports the other items. The report lists the item with the reason.missing or error
Write a blank row for itWrites one row for the item with an empty value: for a timeseries at the end of its range, for a curve at the export date with no tenormissing
Use the latest earlier dataFor a timeseries, the latest value before the end of its range. For a curve, the latest curve before the export date, cut to the tenors. Only data from the Look back up to days before is used. The rows keep the export date and say where the data came from in from. Master data and curves saved for one ondate have no earlier data, so they are left out.previous, with from
Stop the exportStores nothing and sends nothing, and the run of the process fails with the list of items without dataThe process run is failed

Northgate Energy's ETRM must have a price for every item every day, so the team uses Use the latest earlier data with a look back of 10 days. On 19 October the German power base price and the TTF futures curve were late, so the report used their values of 16 October, the Friday before:

idondateindexvaluestatusfrom
EEX_DE:BASE2026-10-19111.22previous2026-10-16
ICE_TTF_FUT:SETTLE2026-10-19M0132.011previous2026-10-16

The ETRM can see from status and from which prices are rolled forward.

note

An event list is never filled from earlier events: yesterday's trades are not today's. With Write a blank row for it or Use the latest earlier data, an event list with no events is left out and listed as missing. With Try again later the run waits for its events like any other item, and with Stop the export a missing event list stops the run. For a list where a quiet day is normal, such as broker confirmations on a day with no broker trades, tick No events is normal for this list in its filter.

caution

Use the latest earlier data sends yesterday's numbers as today's. Only use it when the receiving system can handle that, or when it reads status. Otherwise prefer Leave the item out, or Stop the export with an automation on the process failing so someone is told.


Gaps inside a timeseries range​

When a schedule exports more than one date of a timeseries, for example The last days up to the export date, some dates in the range may have no value. The dates expected are the business days of the schedule's Calendar.

ChoiceWhat happens
Leave the gapsOnly the values there are exported
Write a blank row for each gapA row with an empty value and status missing for each date without one
Fill each gap with the previous valueThe value before the gap is repeated, with status previous and the date it came from in from. A gap at the start of the range stays a gap.

The item's status in the report is partial when gaps were filled, with how many. Gap filling is meant for daily timeseries: intraday values are not expected on calendar dates.


Try again later​

A run can wait for late data instead of deciding straight away. Set Try again later to every 15 minutes, 30 minutes or an hour, and Until to a time in UTC.

When an item has no data, the run checks whether the next try would still be before Until. If it would, the run stores nothing and the process is rescheduled. Otherwise the run applies When an item has no data and stores the report. Each try is shown in Recent runs with status reschedule and the message Trying again in 30 minutes, until 20:00 UTC.

ExampleRuns
Runs at 17:00 UTC, every 30 minutes until 20:00 UTC17:00, 17:30, 18:00, 18:30, 19:00, 19:30, and at 20:00 it decides
The data arrives at 18:10 UTC17:00, 17:30, 18:00, and at 18:30 every item has data and the report is stored
note

Until is in UTC. UK time is UTC in winter and an hour ahead in summer, so 20:00 UTC is 20:00 UK time in winter and 21:00 in summer.

A run for an earlier date (Run for this date) never tries again: it applies the rules straight away.


Choosing the rules​

NeedRules
The receiver must get every item, and can use the previous day's valueUse the latest earlier data, with retries until shortly before the receiver loads
The receiver must never get rolled forward pricesLeave the item out or Stop the export, with retries
The receiver expects a fixed set of rowsWrite a blank row for it, and Write a blank row for each gap for ranges
Someone has to act when data is missingStop the export, and an automation on the process failing, for example an email to the data team